40 lines
2.2 KiB
Plaintext
40 lines
2.2 KiB
Plaintext
|
Madagascar 0.99999 25/02/2015 09:45:59 amd64 1-core (no VSIDS)
|
||
|
Options: file:/home/pluehne/Documents/ASP/pddl-instances/ipc-1998/domains/logistics-round-1-strips/domain.pddl file:/home/pluehne/Documents/ASP/pddl-instances/ipc-1998/domains/logistics-round-1-strips/instances/instance-1.pddlignoring --stats
|
||
|
ignoring --verbose
|
||
|
|
||
|
Domain: logistics-strips
|
||
|
Problem: strips-log-x-1
|
||
|
Parser: 1368 ground actions and 266 state variables
|
||
|
Invariants: 0 1 2 3 4 5 0.01 secs
|
||
|
Goal: conjunctive
|
||
|
Simplified: 360 ground actions and 144 state variables
|
||
|
Actions: STRIPS
|
||
|
Disabling graph %: 10 20 30 40 50 60 70 80 90 100 0.00 secs (max SCC size 1)
|
||
|
Plan type: E-step
|
||
|
Allocated 32 MB permanent (total 123 MB)
|
||
|
Horizon 5: 2664 variables
|
||
|
5 UNSAT (0 decisions 0 conflicts)
|
||
|
Horizon 7: 3672 variables
|
||
|
SAT (90 decisions 0 conflicts)
|
||
|
PLAN FOUND: 7 steps
|
||
|
STEP 0.0: drive-truck(truck6,city6-1,city6-2,city6) fly-airplane(plane2,city4-2,city1-2) load-airplane(package5,plane1,city4-2) load-truck(package3,truck1,city1-1) load-truck(package4,truck1,city1-1) load-truck(package6,truck3,city3-1)
|
||
|
STEP 0.1: drive-truck(truck1,city1-1,city1-2,city1) drive-truck(truck3,city3-1,city3-2,city3) fly-airplane(plane1,city4-2,city6-2)
|
||
|
STEP 1.0: load-airplane(package2,plane2,city1-2) unload-airplane(package5,plane1,city6-2) unload-truck(package3,truck1,city1-2) unload-truck(package4,truck1,city1-2) unload-truck(package6,truck3,city3-2)
|
||
|
STEP 1.1: fly-airplane(plane1,city6-2,city3-2) fly-airplane(plane2,city1-2,city3-2)
|
||
|
STEP 2.0: fly-airplane(plane1,city3-2,city1-2) load-airplane(package6,plane2,city3-2)
|
||
|
STEP 2.1: fly-airplane(plane2,city3-2,city1-2)
|
||
|
STEP 3.0: load-airplane(package3,plane2,city1-2) load-airplane(package4,plane1,city1-2) unload-airplane(package6,plane2,city1-2)
|
||
|
STEP 3.1: fly-airplane(plane1,city1-2,city3-2) fly-airplane(plane2,city1-2,city6-2)
|
||
|
STEP 4: unload-airplane(package2,plane2,city6-2) unload-airplane(package3,plane2,city6-2) unload-airplane(package4,plane1,city3-2)
|
||
|
STEP 5.0: load-truck(package3,truck6,city6-2)
|
||
|
STEP 5.1: drive-truck(truck6,city6-2,city6-1,city6)
|
||
|
STEP 6: unload-truck(package3,truck6,city6-1)
|
||
|
30 actions in the plan.
|
||
|
total time 0.02 preprocess 0.01
|
||
|
total size 352.000 MB
|
||
|
max. learned clause length 0
|
||
|
t val conflicts decisions
|
||
|
5 0 0 0
|
||
|
7 1 0 90
|
||
|
|